Manakamna 7 construction Update 30th of April on all 7 Blocks
The construction progress of Manakamna 7 residential project has been going smoothly and the latest update on 30th April 2023 confirms all seven blocks are in full phase and nearing completion. The project is expected to be ready for habitation by December 2023, as previously scheduled. The construction work has already reached the 80-90% completion mark, and buyers can expect to move into their new homes soon. Detailed updates on the construction progress of all seven blocks are available for interested parties to review. Overall, the project has been progressing well, and the developers are optimistic about its timely completion.
Construction Update of Block 1
- The roof casting for the building is now finished.
- The plastering work has been completed on the 1st and 2nd floors, with the 3rd floor currently in progress.
- Block work on the 4th and 5th is ongoing.
- The workers are currently applying the outside plaster.
- The construction team is currently working on parapet wall and pergola installation.
- The first, second, and third kitchen granite installations are finished.
- Stair cota installation has been completed successfully.
- Plumbing on 1st & 2nd floor done, 3rd floor in progress.
The construction progress of Block 1 is well on track. With construction on Block 1 proceeding as planned, interested buyers can purchase a unit and expect to move in by December 2023.
Construction Update of Block 2
- The construction team has successfully completed the roof casting process.
- The internal plaster of Block 2 in is finished.
- The brickwork construction has completed.
- The outside plaster of Block 2 is almost finished, reaching 90%.
- The granite work for the kitchen has been completed for all flats.
- The installation of staircase cota has been successfully completed.
- The stair railing installation has been completed as scheduled.
- The construction of the AC ledge grill is 50% complete.
- The plumbing work for Block 2 has been completed.
- The construction of parapet and parabola walls has been completed.
- The civil work for the landscape (roof) has been completed.
- Plumbing work on the ground floor is currently underway.
Block 2 construction in Manakamna 7 is progressing well, and interested buyers can purchase their new homes now. The construction is on full swing, and the block is expected to be ready for move-in by December 2023.
Construction Update of Block 3
- The roof casting for Block 3 has been successfully completed.
- The brick work of Block 3 is now completed.
- The plastering work has been completed.
- All plumbing and electrical work for Block 3 has been completed.
- The kitchen slab and granite work are finished.
- The installation of staircase railings has been completed successfully.
- The fixing of staircase and balcony railings has been completed.
- The construction of the AC Ledge is halfway through completion.
- The construction work on the over roof parapet wall and parabola is finished.
- The fixing of the main door and lock has been completed.
- The landscape civil work for the project has been fully completed.
- The plumbing work on the ground floor is currently underway.
The progress of Block 3 construction in Manakamna 7 is ongoing and is expected to be completed on time. The block is expected to be habitable by December 2023, as planned. Overall, the construction of the project is going well.
Construction Update of Block 4
- Important tasks such as roof casting, plastering, brickwork, plumbing, electrical work, staircase and balcony railing, AC ledge grill fixing, kitchen slab, and cota fixing all being completed.
- The roof parapet wall, Parbola landscape, and civil wall are all finished.
- The water-proofing measures is ongoing.
- The fixing of main doors with locks has been completed up to the 4th floor.
The construction progress of Block 4 in Manakamna 7 is going well, and it has reached the 80-90% completion mark. The block is expected to be ready for habitation by December 2023, as planned.
Construction Update of Block 5
- Several key aspects of construction were completed, such as roof casting, plastering, brickwork, plumbing, electrical work, stair and balcony railing installation, AC ledge grill fixing, and kitchen slab and cota fixing.
- Construction milestones of roof parapet wall, Parbola landscape, and civil wall completed.
- The ongoing construction work includes waterproofing measures for the building.
- The fixing of main doors with locks has been completed up to the fourth floor.
The work on the 4th floor of the building is finished, while the 5th and 3rd floors are 50% complete.
- The process of water proofing is currently underway.
Block 5 in Manakamna 7 is also progressing rapidly, and interested buyers can make their purchases now. The construction work is expected to be completed on time, and buyers can expect to move into their new homes by December 2023 as well.
Construction Update of Block 6
- The construction project's roof, brick work, electrical, and staircase installation are finished.
- The plumbing has been completed up to the 3rd floor successfully.
- The plastering work for the 4th and 5th floors is ongoing inside the building.
- The exterior plastering work is currently ongoing.
- The construction work on the roof parapet wall and parabola has been completed.
The construction of Block 6 is progressing rapidly, with the project currently in full swing. Significant progress has been made, and the construction is on schedule to be completed on time.
Construction Update of Block 7
- The construction project has completed the casting of up to fifth-floor.
- The construction workers are currently casting the roof on the 5th floor.
The brick work for the 1st floor is complete, while the 2nd and 3rd floors are currently in progress.
The construction of Block 7 of Manakamna 7 is progressing at a satisfactory rate, and based on the current pace, it is expected to be completed on time. We will continue to monitor the progress closely and ensure that the project remains on track.
2 Comments